Planning and Decision Making mixed revision quiz

A mixed adaptive checkpoint across activity networks, PERT, critical path, Gantt charts, expected value and risk decisions.

Quick checkpoint

Check your understanding

Answer each question, check the feedback, then use the diagnosis to target the planning or decision skill that needs more practice.

Score: 0/12

Question 1

In an activity network, what does a dependency show?

activities and dependencies
Choose an answer

Question 2

In a PERT activity network, A and B start at time 0 and take 2 and 5 days. C takes 3 days and starts only after both finish. Find the earliest project completion time.

PERT networks

Question 3

Find float if earliest start is 6 and latest start is 9.

float

Question 4

What is true about a critical activity?

critical path
Choose an answer

Question 5

Expected value is best described as:

expected value
Choose an answer

Question 6

Tasks A (2 days) and B (5 days) have no predecessors, but both require the same specialist full-time and cannot be split. One specialist is available throughout. What is the earliest completion time for both tasks, and why?

interpreting decisions
Choose an answer

Question 7

Which chart is best for showing activities across a timeline?

Gantt charts
Choose an answer

Question 8

Which activity is critical?

critical path
Choose an answer

Question 9

Find expected value for 0.25 chance of 200 and 0.75 chance of 40.

expected value

Question 10

What should be considered in a risk decision besides expected cost?

risk
Choose an answer

Question 11

During a forward pass, if two predecessor activities finish at 6 and 9, what earliest start should be used?

critical path
Choose an answer

Question 12

A network gives a 12-day project duration using estimated activity durations. Why might actual completion be later?

PERT networks
Choose an answer